Carnegie-Pittsburgh Theater Progress Report 8-21-12
Air condition unit and ducts moved from stage area to lobby. Risers finished, waiting for carpeting.
Stage floor ready for MDF board. Electric wiring run. Drywall going up tomorrow.
Trussing for lighting grid on its way. Should be able to "dance" on stage this weekend.
Next week, painting, painting and last but not least - plumbing. New entrance doors and awnings hopefully in next week. Stay tuned for further updates.
Stage floor ready for MDF board. Electric wiring run. Drywall going up tomorrow.
Trussing for lighting grid on its way. Should be able to "dance" on stage this weekend.
Next week, painting, painting and last but not least - plumbing. New entrance doors and awnings hopefully in next week. Stay tuned for further updates.